Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/15/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Clear sky, no wind, 80 degrees <br /> From: 7:30 To: 17:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 10 Kessler Reclamation 7 10 <br /> Joe Kaul 1 3 <br /> Ryan Anderson 1 2 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Pump trailer 1 10 <br /> Description of Work Performed: <br /> Pouring concrete into the GeoWeb, starting from the top of alignment <br /> 36 CY of concrete poured 230 feet of the channel. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Inspector: Sam Lowe Date: 10/15/2020 <br />