Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/8/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, no wind, 75 degrees <br /> From: 12:00 To: 13:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 5 5 <br /> H&H Lining 3 10 <br /> Joe Kaul 1 7 <br /> Contractor Equipment No Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Small Excavator 1 5 <br /> Description of Work Performed: <br /> H&H completed the GeoWeb install. Kessler's began backfilling the key in trenches. <br /> Billy Ray was on site for an inspection with DRMS. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> The anchor point from the GeoWeb to the headwall will be completed tomorrow morning. H&H should <br /> done by the end of the day with their work on the channel. <br /> Inspector: Evan Valencia Date: 10/8/2020 <br />