Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/6/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Clear sky, no wind, 75 degrees <br /> From: 12:00 To: 13:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. <br /> Hours (by Labor Class) No. <br /> Hours <br /> Oversight (Sam Lowe) 1 5 JKessler Reclamation 5 10 <br /> H&H Lining 3 10 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Skidster 1 10 <br /> Description of Work Performed: <br /> Kessler finished digging the key-in trenches at the bottom of the alignment. <br /> Meanwhile, H&H installed the bottom Geotextile layer; they used a torch to "weld" the seams together. <br /> Next they laid the Geomembrane liner.The weld was performed by a DemTech Pro Wedge welder. <br /> Finally they laid the top layer of geotextile. They need to grab another roll tomorrow morning to finish. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Sam Lowe Date: 10/6/2020 <br />