Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/30/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, 65 degrees <br /> From: 14:00 JNo. <br /> 16:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 2 Kessler Reclamation 5 11 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 2 Excavator 1 11 <br /> Loader 1 11 <br /> Haul Truck 1 11 <br /> Skid Loader 1 11 <br /> Description of Work Performed: <br /> The excavation of the channel began today, with progress around 100 ft from headwall. <br /> A custom bucket was created by Kessler to dig the channel to the design dimensions.The small excavator <br /> was used to dig the two key-in trenches outside of the main ditch. Kessler measured the dimensions of the <br /> channel as excavation progressed to ensure the correct size and shape. <br /> More material was screened to complete the road in the coming days. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> The geoweb technicians are expected to be on site on Monday for prep work and training. <br /> The excavation of the channel should be completed on Monday for the geoweb team to begin work <br /> on Tuesday. <br /> Inspector: Evan Valencia Date: 9/30/2020 <br />