Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/1/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, no wind, 65 degrees <br /> From: 6:00 To: 17:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Isaac Gonzalez) 1 3 Kessler Reclamation 5 11 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 2 Excavator 1 11 <br /> Loader 1 11 <br /> Small excavator 1 11 <br /> Description of Work Performed: <br /> Excavation of the open conveyance continued today. A custom bucket was created by Kessler to dig <br /> the channel to design criteria. A small excavator was used to dig the two channels outside of the main ditc <br /> for keying in the liner material. Kessler measured the dimensions of the channel as excavation progressed <br /> to ensure the correct size and shape. Material screening continued in anticipation to complete the road. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> The geoweb technicians are expected to be on site on Monday for prep work and training. <br /> The excavation of the channel should be completed on Monday for the geoweb team to begin work <br /> on Tuesday. <br /> Inspector: Isaac Gonzalez Date: 10/1/2020 <br />