Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/1/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear, 75 degrees <br /> From: 7:30 To: 15:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. <br /> Hours (by Labor Class) No. <br /> Hours <br /> Oversight (Sam Lowe) 1 4 Kessler Reclamation 6 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 2 Excavator 1 8 <br /> Haul truck 2 8 <br /> Loader 1 2 <br /> Skid Steer 2 8 <br /> Description of Work Performed: <br /> Kessler Reclamation continued excavation down the channel/ road. Excavated material is being stored <br /> temporarily in the valley floor to minimize haul truck driving time and shorten the total excavation time. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Sam Lowe Date: 9/1/2020 <br />