Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/31/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Partly Cloudy, 75 degrees <br /> From: 13:00 To: 14:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 6 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 8 <br /> Haul truck 2 8 <br /> Bull Dozer 1 8 <br /> Skid Steer 2 8 <br /> Description of Work Performed: <br /> Kessler Reclamation continued excavation down the channel / road. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Skid steer track spring broke and halted progress. Kessler's going to get parts repaired today. <br /> Inspector: Evan Valencia Date: 8/31/2020 <br />