Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/28/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, smoky, 98 degrees <br /> From: 13:00 To: 14:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No Hours (by Labor Class) No. Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 6 8 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Excavator 1 8 <br /> Haul truck 2 8 <br /> Bull Dozer 1 8 <br /> Skid Steer 2 8 <br /> Description of Work Performed: <br /> After taking 8/27 to work on other excavation projects, Kessler Reclamation continues initial excavation fo <br /> diversion channel, with the expectation to complete initial excavation on Monday. <br /> Berm constructed at end of excavation to prevent rain over the weekend to leave the area. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Herc Rentals has a 2,000 gal gasoline truck available for the next month. Kessler Reclamation organizing <br /> account to secure reservation for next week. <br /> Billy Ray on-site to see progress. <br /> Inspector: Evan Valencia FDaTt8/28/2020 <br />