Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/25/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, smoky, 98 degrees <br /> From: 6:00 To: 16:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Tyler Fasenmyer) 1 2 Kessler Reclamation 6 10 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Excavator 1 10 <br /> Haul truck 2 10 <br /> Bull Dozer 1 10 <br /> Skid Steer 2 10 <br /> Description of Work Performed: <br /> Continue initial excavation for diversion channel. Kessler Reclamation continued to prepare diversion <br /> Channel by rough digging area to engineered depth.The excavated soil is loaded into two alternating <br /> haul trucks and either stock piled or disposed of in the open hole located in the Minnesota adit. <br /> Following the initial dig a bulldozer is used to grade and control soil for further soil loading. <br /> Skid steers are used to consolidate excavated soil underground. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Kessler is having trouble finding a rental water truck for dust mitigation and material packing. <br /> Will follow up with Herc Rentals for availability. <br /> Inspector: Tyler Fasenmyer Date: 8/25/2020 <br />