Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/24/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, smoky, 90 degrees <br /> From: 13:00 To: 14:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No. <br /> Hours <br /> Oversight (Evan) 1 1 Kessler Reclamation 6 8 <br /> Contractor Equipment No Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 5 <br /> Haul truck 2 5 <br /> Presence of Water: No Description: No longer visible due to first pour of wall. <br /> Description of Work Performed <br /> Excavation continues for the ditch. About 1/3 of the way down the hill. <br /> Air samples from Friday surveyed. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Kessler is having trouble finding a rental water truck for dust mitigation and material packing. <br /> Inspector: Evan Valencia Date: 8/24/2020 <br />