Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/19/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, slight Haze from fires, 95 degrees <br /> From: 9:00 JNo. <br /> 15:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) Hours (by Labor Class) No Hours <br /> Oversight (Isaac) 2 Kessler Reclamation 2 6.5 <br /> Oversight (Sam) 1 1 <br /> Oversight (Chris) 1 1 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger Truck 1 1 Excavator 1 6.5 <br /> Air sampler 1 2 Haul truck 1 6.5 <br /> Electric Generator 1 2 <br /> Presence of Water: No Description: No longer visible due to first pour of wall. <br /> Description of Work Performed <br /> Excavation started for the ditch, general air sample collected for gross alpha counting. Excavated material <br /> is being stockpiled in the valley floor, this significantly cuts down on haul truck time. About 12 minutes <br /> for haul truck to return after loaded, takes about 7 minutes to fill haul truck. Chris, Sam and myself also <br /> walked the planned excavation area and updated the baseline gamma exposure readings to match lath <br /> locations. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Work is moving faster than anticipated after approval to stage excavated material in valley floor, <br /> Kessler hopes to be done with excavating material by the end of this Friday. <br /> Inspector: Isaac Gonzalez Date: 8/19/2020 <br />