Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/18/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, slight Haze from fires, 95 degrees <br /> From: 10:30 To: 13:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam) 1 2.5 Kessler Rec. 2 8 <br /> Tot <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. Hours <br /> Excavator 1 4 <br /> Haul truck 1 4 <br /> Presence of Water: No Description: No longer visible due to first pour of wall. <br /> Description of Work Performed <br /> No work performed on the NWRP in the AM. <br /> Afternoon, Calvin and Wayne were going to start into excavation along the alignment. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Calvin and Sam discussed the future sequence of the earth work. Kessler will start excavating <br /> to—8" below finished ditch grade. Then they will build up the alignment with clean fill until up to <br /> top of ditch bank elevations. Then they will excavate out the trapezoidal ditch section. <br /> Minor cleanup at the wall's trapezoid section was discussed; grout some small voids and grind any <br /> sharp edge or abnormality to limit chance of concrete damaging the geomembrane. <br /> Kessler sees hauling the contaminated fill directly to the Minnesota adit as time prohibitive and <br /> is hoping to get approval to stockpile fill in the valley bottom to keep NWRP productivity high. <br /> Inspector: Sam Lowe Date: 8/18/2020 <br />