Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/17/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, Haze from fires, 90 degrees <br /> From: 8:00 To: 15:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Isaac) 1 4 Kessler Rec. 5 6.5 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> None Passenger Vehicles 2 6.5 <br /> Excavator 1 0.5 <br /> Skid Loader and parts 2 2.5 <br /> Presence of Water: No Description: No longer visible due to first pour of wall. <br /> Description of Work Performed <br /> Routine maintenance of skid loaders and other equipment. Trained Calvin and Wayne Kessler on <br /> equipment surveys and gamma exposure readings. Broke down forms for concrete wall. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Invert on cement wall does not measure to the expected specifications.The invert plus the geomembrane <br /> liner should be two feet below the Top-of-Wall, however the current cement wall has an invert that is itself <br /> two feet below T.O.W. Sam Lowe has been notified of this deficiency. <br /> Inspector: Isaac Gonzalez Date: 8/17/2020 <br />