Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/11/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 80 degrees <br /> From: 6:00 To: 16:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Tyler) 1 3 Kessler Reclamation 5 10 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Pickup Truck 1 1 <br /> Description of Work Performed <br /> Kessler Reclamation Constructed form for cut off wall. Holes were drilled into rock sides and rebar <br /> was installed. Personnel cut and fit wood concrete forms to fit in rock areas. <br /> Personnel cut out form for cutoff wall spill way. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Tyler Fasenmyer Date: 8/11/2020 <br />