Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/10/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 70 degrees <br /> From: 9:00 To: 4:00pm <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Isaac) 1 5 Kessler Reclamation 6 6 <br /> Contractor Equipment No. Hours Subcontractor Equipment No. Total <br /> Pickup Truck 1 3 Topcon Level 1 5 <br /> Hand Tools 1 5 <br /> Description of Work Performed <br /> Kessler broke down wood structure to hold rebar and verified distances between rebar sticks. Calvin took <br /> elevation measurements with topcon level to note top-of-channel. Crew broke up and removed loose rock <br /> where concrete form will go. Calvin and crew also measured and cut particle board to fit snug to the walls <br /> of the channel. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Isaac Gonzalez Date: 8/10/2020 <br />