Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 8/7/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 80 degrees <br /> From: 9:00 To: 11:00am <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam) 1 1 Kessler Reclamation 3 3 <br /> AGW 1 2 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Pickup Truck 1 1 Gator 1 0.5 <br /> Honda Generator 1 1 <br /> Concrete Vibrator 1 1 <br /> Description of Work Performed <br /> I checked rebar at 7:30am; 12-inch spacing vertically and horizontally throughout first 5 feet. <br /> Escorted AGW technician plus two concrete trucks at 9:05. Returned for 3rd truck. <br /> Placed all 18 CY of concrete; the pour was a couple inches higher than Calvin had thought. <br /> Kessler embedded a 2x4 between the rebar to act as a key trench for 2nd pour. <br /> AGW technician grabbed a sample of subgrade fill from the pile at the "Double O". <br /> Sam and Calvin discussed Sam's proposed vertical invert adjustments to the middle portion of the <br /> ditch. Sam change cut depths accordingly and made sure Calvin's plans matched Sam's. <br /> Remarks b Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Y ( Y P <br /> Monday (8/10) Kessler will start forming top section of the seal wall. <br /> Discussed logistics of placing PVC pipe, gravel and riprap above the seal wall. <br /> Inspector: Sam Lowe Date: 8/7/2020 <br />