Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/15/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, 80 degrees <br /> From: 8:00 To: 16:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Isaac Gonzalez) 1 4 Kessler Reclamation 5 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 3 Excavator 1 8 <br /> Loader 1 8 <br /> Water Truck 1 8 <br /> Haul Truck 1 8 <br /> Skid Loader 1 8 <br /> Description of Work Performed: <br /> Material screening continued.Temporarily stored dirt hauled into Minnesota Adit onsite. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> No remarks, screening material tomorrow also. <br /> Inspector: Isaac Gonzalez Date: 9/15/2020 <br />