Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/16/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Light haze from smoke; 65-70 degrees <br /> From: 8:00 To: 16:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No Hours (by Labor Class) No. Hours <br /> Oversight (Sam Lowe) 1 4 Kessler Reclamation 3 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 2 Excavator322C L 1 8 <br /> Loader950G 1 8 <br /> Water Truck 1 8 <br /> Grizzley Screen <br /> Description of Work Performed: <br /> Material screening continued. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Calvin's plan is to screen today and tomorrow. Start placing fill on Friday. <br /> Inspector: Sam Lowe Date: 9/16/2020 <br />