066B Haul Cuttings to NW Mains Vent Shaft for TRUCKI 1 40.44 $90,170
<br /> Backfill
<br /> 066C NW Mains Vent Shaft-Push Cuttings Into Pit DOZER 1 12.23 $4,455
<br /> 066D Backfill geotechnical test-pits,MR295 EXCAVATE 1 14.86 $1,129
<br /> 066E Backfill and Grade 9 East Utility Borehole Pad DOZER 1 6.35 $2,464
<br /> 066F Permanent Coal Fine Disposal from FCB Spill; TRUCKI 1 1.72 $533
<br /> MR297
<br /> 067 Compact Coal Stockpile Footprints at Refuse Pile COMPACT 2 181.24 $94,112
<br /> 068 Compact Temporary Storage Refuse in Area 3 COMPACT 2 17.52 $9,098
<br /> 070 Regrade,Disperse Surfacing,and Rip Main Haul DOZER 1 21.15 $8,397
<br /> Road
<br /> 071 Regrade,Disperse Surfacing,and Rip Haul Road B DOZER 2 28.14 $22,354
<br /> 073 Regrade,Disperse Surfacing,and Rip Haul Road C DOZER 2 7.79 $6,186
<br /> 074 Regrade,Disperse Surfacing,and Rip Shop Access DOZER 2 5.81 $4,617
<br /> Road
<br /> 075 Regrade and Rip Explosives Storage Area Access DOZER 1 9.82 $3,900
<br /> Road
<br /> 076 Regrade,Disperse Surfacing,and RipBrown DOZER 1 6.06 $2,405
<br /> Palace Access Road
<br /> 077 Regrade,Disperse Surfacing,and Rip Training DOZER 1 8.02 $3,184
<br /> Center Access
<br /> 078 Regrade,Disperse Surfacing,and Rip Weigh DOZER 1 11.10 $4,408
<br /> Station Access
<br /> 079 Regrade,Disperse Surfacing,and Rip Fish Creek DOZER 1 5.29 $2,100
<br /> Bore Access
<br /> 080 Regrade,Disperse Surfacing,and Rip Fish Creek DOZER 1 14.38 $5,710
<br /> Tipp Access
<br /> 082 Regrade and Rip Equipment Storage Area and DOZER 1 5.08 $2,018
<br /> Access Road
<br /> 083 Regrade and Rip Pond T Access Road DOZER 1 0.85 $337
<br /> 084 Regrade and Rip Wastewater Facility Ramp and DOZER 1 26.04 $10,341
<br /> Access Road
<br /> 085 Regrade and Rip 6 North Main Ditches and Access DOZER 1 8.48 $3,368
<br /> Road
<br /> 086 Regrade and Rip 16 Left Grout Borehole Access DOZER 1 1.18 $468
<br /> Road
<br /> 087 Regrade and Rip 16LT Utility Borehole Access DOZER 1 43.42 $17,243
<br /> Road
<br /> 088 Regrade and Rip 15LT Vent Shaft Access Road DOZER 1 2.74 $1,088
<br /> 089 Rip and Bulldoze Surface Material on Northwest DOZER 1 6.97 $2,768
<br /> Vent Shaft Pa
<br /> 090 Rip West Haulroad Truck Scale and Ramp RIPPER 1 3.18 $1,263
<br /> 091 Remove Gravel Fill at Batch Weigh Haulroad TRUCKI 1 7.04 $7,840
<br /> 092 Load/Haul Northwest Main Vent Shaft Pad and TRUCKI 1 13.58 $15,418
<br /> Access Road Mate
<br /> 093 Remove Gravel from 6 North Main Access Road TRUCKI 1 3.90 $2,917
<br /> 094 Remove Gravel from West Haulroad TRUCKI 1 1.67 $1,251
<br /> 095 Remove and Haul Parking Expansion Asphalt TRUCKI 1 1.63 $1,046
<br /> 096 Remove 18 Left Vent Shaft Pad,Substation and TRUCKI 1 11.53 $14,466
<br /> Access Road Ma
<br /> 097 Remove Refuse Disposal Area Expansion SCRAPERI 1 5.28 $6,323
<br /> Haulroad Base
<br /> 098 Regrade Access Roads;TRO Coal Quality DOZER 1 19.44 $5,041
<br /> Coreholes 5-10,MR272
<br /> 099 Regrade Light-Use Road;5MN Borehole MR283 DOZER 1 6.96 $2,397
<br /> 100 Rip New CRDA Topsoil Stockpile Access Road; RIPPER 1 0.82 $289
<br /> MR290
<br />
|