TASK 001 STRUCTURE DEMO BREAKDOWN
<br /> Structure or Item Description Dimensions Demolition Quantity Unit Unit Cost Total Cost SL5
<br /> Menu Selection
<br /> -Footers 1'x2'x334 Demo.and on- 334.00 LF $3.58 $1,195.72
<br /> LF site disposal in excavated pit,
<br /> 1.0 ft.x 2 ft.-Max.200 ft.
<br /> push $1195.72
<br /> -Pad 1'x2'x4" Demo.and on-site disposal in excavated pit,4 7,000.00 SF $0.57 $3,983.00
<br /> in.thick-Max.200 ft.
<br /> push $3983.00
<br /> 500 Gallon Antifreeze Tank;#5 Fuel 500 Gallons Comprehensive storage tank removal,non- 1.00 EA $3,409.60 $3,409.60
<br /> Island leaking-3,000
<br /> to 5,000 gal.tank $3409.60
<br /> 8000 Gallon Diesel Fuel Tank;#5 8000 Comprehensive storage tank removal,non- 1.00 EA $5,286.80 $5,286.80
<br /> Fuel Island Gallons leaking-6,000
<br /> to 8,000 gal.tank $5286.80
<br /> 2000 Gallon Oil 2000 Comprehensive 1.00 EA $5,286.80 $5,286.80
<br /> Tank;#5 Fuel Island Gallons storage tank $5286.80
<br /> 1000 Gallon Gasoline Tank;#5 Fuel 1000 Comprehensive storage tank removal,non- 1.00 EA $3,409.60 $3,409.60
<br /> Island Gallons leaking-3,000
<br /> to 5,000 gal.tank $3409.60
<br /> 1375 Gallon Oil Tank:#5 Fuel Island 1375 Comprehensive storage tank removal,non- 1.00 EA $3,409.60 $3,409.60
<br /> Gallons leaking-3,000
<br /> to 5,000 gal.tank $3409.60
<br /> 275 Gallon 275 Gallons Comprehensive storage tank removal,non- 1.00 EA $3,409.60 $3,409.60
<br /> Antifreeze;#5 Fuel Island leaking-3,000
<br /> to 5,000 gal.tank $3409.60
<br /> 500 Gallons Used Oil;#5 Fuel Island 500 Gallons Comprehensive storage tank removal,non- 1.00 EA $3,409.60 $3,409.60
<br /> leaking-3,000
<br /> to 5,000 gal.tank $3409.60
<br /> Rock Dust Tank;Empire Village 8'D x 20' Bldg.(MN)demo./on-site disposal in excavated 1,005.00 CF $0.22 $217.08
<br /> pit-Max.200 ft.push $217.08
<br /> 2 Rock Dust Tanks; 8'D x 20' Bldg.(MN) 2,010.00 CF $0.22 $434.16
<br /> Shop area (2) demo./on-site disposal in excavated pit-Max.
<br /> 200 ft.
<br /> push $434.16
<br /> Rock Dust Tank;#5A Portal Area 8'D x 20' Bldg.(MN)demo./on-site disposal in excavated 1,005.00 CF $0.22 $217.08
<br /> pit-Max.200 ft.
<br /> push $217.08
<br /> Bathouses Near Mine Office 24'x 50' Bldg.(SN)demo./on-site disposal in excavated 43,200.00 CF $0.20 $8,510.40
<br /> (Men's,Womens and Visitor x12(3) pit-Max.200 ft.
<br /> push $8510.40
<br /> No.5 Mine Conveyor 380 LF(?) Conveyor,Horizontal Belt 24"Belt,61.5' 6.00 EA $2,825.00 $16,950.00
<br /> Length $16950.00
<br /> No.5A Conveyor and 120 LF Conveyor, 2.00 EA $2,825.00 $5,650.00
<br /> Transfer(Mine Overland) Horizontal Belt 24"Belt,61.5'
<br /> Length $5650.00
<br /> 48-Inch Overland Conveyor(Mine 1712 LF Conveyor,Horizontal Belt 24"Belt,61.5' 28.00 EA $2,825.00 $79,100.00
<br /> Overland) Length $79100.00
<br /> Stacking Tube 85'x 12'D Bldg.(MN)demo./on-site disposal in excavated 9,613.00 CF $0.22 $2,076.41
<br /> pit-
<br /> Max.200 ft.push $2076.41
<br /> Reclaim Tunnel 4 @ 270' Demo.and on-site disposal in excavated pit,12 14,040.00 SF $1.71 $23,952.24
<br /> x13'x12" in.thick-Max.200 ft.push $23952.24
<br /> Reclaim Tunnel 300 LF Conveyor, 5.00 EA $2,825.00 $14,125.00
<br /> Conveyor Horizontal Belt 24"Belt,61.5'
<br /> Length I 1 1 $14125.00
<br /> Screening and Sizing Building 70'x 60'x Bldg.(MN)demo./on-site disposal in excavated 168,000.00 CF $0.22 $36,288.00
<br /> 40' pit-
<br /> Max.200 ft.push $36288.00
<br /> 2