EXHIBIT L RECLAMATION COSTS(CONT) <br /> according to our records . Total dewatering time includes 36 . 6 <br /> days to pump the lake, 5 . 8 days to build slopes and 0 . 35 days to <br /> pump recharge . The total pumping time is rounded to 43 . 0 days . <br /> The settling ponds areas can be filled to a level 2 foot over the <br /> ground water table, so no dewatering cost is included for Phases <br /> lA and 2A. Phase 1 sloping below the water line is complete . <br /> The equipment used in the estimate is. <br /> Scraper teams - 2-Cat 627G scraper, D9R Dozer, 140H grader & <br /> water truck - Resoiling & backfilling <br /> Grader - Cat 140H - seedbed prep and ripping plant site <br /> Dozers - 2 - Cat D9R - cut/fill working face sloping <br /> Dewatering Pump data 3-600M (6000 gpm each) , 1511 , 121'suction & <br /> discharge hoses - total (18 , 000gpm) <br /> Seeding team - standard farm tractor and pull behind drill , and <br /> crimping disk attachment <br /> L.G. Everist,Inc. Ragsdale Reservoirs May 5,2020 <br /> 82 <br />