Reclamation Ridge, LLC. Technical Revision 03 <br /> Thompson Resource August2l, 2018 <br /> M-1983-102 <br /> Using the November 16 , 2009 Circes Cost Estimate as a basis for <br /> the bond calculation, I propose eliminating Tasks 006 and 009 <br /> that deal with resoiling and revegetation of the floor and <br /> increasing the following volumes to allow for more disturbance <br /> area. Using the task numbers from the estimate, the proposed <br /> changes are : <br /> 001 WORKING FACE REDUCTION - no change (650 If @ 29.62 cyds/Ift) <br /> 003 GRADE CURRENT STOCKPILES - no change <br /> 004 RESHAPE PIT FLOOR - increase to 28.0 acres (current 24.2 ac) <br /> 005 REPLACE TOPSOIL ON SLOPES - increase to 2825 cyds (3.50 ac @ 6") <br /> 006 Eliminate <br /> 008 HYDROSEEDING SLOPES - increase to 5.7 acres to seed slopes and topsoil piles (2.2 ac) <br /> that would be graded. <br /> 009 Eliminate <br /> O10 MOBILIZATION - Remove Cat 631G scraper and Revegetation equipment that were to be y <br /> used on floor area. <br /> 011 2:1 SLOPE MAINTENANCE - no change <br /> All material needed for industrial area grading and working face <br /> reduction is onsite . There is an estimated 12 , 350 yds topsoil on <br /> site . Attached is a revised Exhibit L - Reclamation Costs based <br /> on these numbers . <br /> Respectfully Submitted, <br /> -�Oz <br /> �— <br /> Ken Evans, Jr. <br /> Manager <br /> PAGE 3 <br />