2. Mining Timetable <br /> The following timetable is a best estimate of the sequence of operations for the life of the mine <br /> after April 2018. Estimates are based on mining and selling 1 million tons of total product per <br /> year: <br /> Table D-1 Mining Timetable <br /> Mining Time Material Quantity <br /> 2018-2020 1500000 Tons <br /> 2020-2025 5000000 Tons <br /> 2025-2030 5000000 Tons <br /> 2030-2035 5000000 Tons <br /> 2035-2038 2900000 Tons <br /> Total 20 Years 19,400,000 Tons <br /> The mining schedule is planned to minimize disturbance by reclaiming areas as additional <br /> mining is undertaken.Note: If large contracts are awarded to the site, production could increase <br /> to the permit maximum,thereby curtailing the life of the pit. On the other hand, if contracts are <br /> less than anticipated,the life of the pit could be extended. This table is based on a reasonable <br /> projection of average production rates. <br /> 3. Mine Facilities and Operation <br /> The site will contain the below listed facilities. Where applicable, it is noted if a facility is <br /> portable and whether it will have any fuel storage associated with it. <br /> - A portable asphalt plant with associated tanks <br /> - A portable concrete plant with associated tanks <br /> - Truck scales <br /> - Mine office <br /> - A portable crusher with associated tanks <br /> - A portable wash plant with associated tanks <br /> - Portable wash plant recycle pond <br /> DMR <br /> April 2018 D-3 <br />