Laserfiche WebLink
CRIPPLE CREEK & VICTOR GOLD MINE <br />NEWMONT MINING CO. <br />SQUAW GULCH VLF WEEKLY REPORT <br />Underground Workings: <br />Blasting: <br />UG #6471 & UG #6679: Previously drilled boreholes were shot. A Cat excavator began <br />removing shot rock. Further remediation required. <br />Confirmatory Drilling: <br />UG #6477: Sandvik 700 –23.0 hours, 2400LF. Further remediation required. <br />UG #6478: Sandvik 700 –5.0 hours,500LF. Further remediation required. <br />Remediation: <br />UG# 6531: The first and second layers of geogrid and Select Structural Fill were placed <br />and compacted.The area was backfilled to design subgrade elevation.All work was <br />completed per project plans and specifications.Remediated. <br />UG# 6478: A Cat excavator removed timbers and filled shaft with approximately 171 <br />cubic yards of Coarse Shaft Backfill. Drill access provided. Further remediation required. <br />T&M = 1.5 hours. <br />UG# 6480: A Cat excavated to competent rock at 19+/-feet. Backfilled and compacted <br />per project specifications. Remediated. T&M = 1.5 hours. <br />UG# 6617: A Cat excavator removed shot rock and prepared the area for additional <br />confirmatory drilling. Further remediation required. <br />UG #6455 & UG #6456: A Cat excavator and Cat dozers removed shot rock in <br />preparation for geogrid subgrade. Further remediation required. <br />Underdrain System: <br />Primary Underdrain:Complete. <br />Secondary Underdrain:None. <br />Tertiary Underdrain:None. <br />Leak Detection: <br />A Cat excavator, a Cat dozer and Cat 740 haul trucks placed SLF in the vicinity of HM13+00 to <br />construct a temporary bench for leak detection.A Cat excavator began preparing the trench for <br />leak detection in the vicinity of station HM13+00. <br />A Cat excavator prepared leak detection trench between stations I4+00 and I8+00.A Cat <br />skidsteer assisted with construction of approximately 350 LF of leak detection per project plans <br />and specifications. <br />All work completed per project plans and specifications. <br />Geomembrane: <br />None. <br />Miscellaneous: <br />None.