Newmont‐Cripple Creek & Victor Gold Mine  <br />Technical Specification No. 02200.DOCX  <br />Squaw Gulch VLF  <br />Project No.475.0106.006  <br />June 15, 2016  <br />  <br />  <br />  <br />Page 2  <br />1.4. Quality Assurance  <br />A. All work shall be monitored and tested in compliance with the requirements of the CQA  <br />Plan.  <br />B. CONTRACTOR shall be aware of all testing activities outlined in the CQA Plan, and shall  <br />account for these activities in the construction schedule.  <br />C. All  CQA  soils  testing  (both  field  and  laboratory  testing)  will be  the  responsibility  of  <br />CERTIFYING ENGINEER, as identified in the Earthworks CQA plan. CONTRACTOR shall be  <br />responsible for cooperating with CQA Monitor during all testing activities. CONTRACTOR  <br />shall provide equipment and labor to assist CQA Monitor in sampling, if requested, and  <br />shall also provide access to all areas requiring testing activities. Quality Control testing  <br />shall be the responsibility of the CONTRACTOR.  <br />D. All  excavation,  backfill,  and  grading  operations  shall  be  carried  out  under  the  <br />observation of MANAGER and CERTIFYING ENGINEER.  <br />E. Any work found unsatisfactory or any work disturbed by subsequent operations before  <br />acceptance is granted shall be corrected by CONTRACTOR, at its sole cost.  <br />2. PART 2: PRODUCTS  <br />2.1. Materials  <br />A. Fill materials will be soils, gravels, or rock fill approved by MANAGER and CERTIFYING  <br />ENGINEER. The materials shall be free of organic matter, debris, frozen material, and  <br />other deleterious materials, and shall be excavated, as required, as follows:  <br />1. Structural  Fill  ‐  material  as  approved  by MANAGER and CERTIFYING  ENGINEER  <br />conforming to the following SPECIFICATION:  <br />  <br />U.S. Standard  <br />Sieve Size  <br />Percent Passing  <br />by Dry Weight  <br />24 – inch  100  <br />No. 200  0 – 25  <br />Plasticity Index:  30 maximum  <br />  <br />2. Select Structural Fill ‐ well graded granular soil or sound, hard, durable, rockfill  <br />excavated  on‐site  or  supplied  from  off‐site  mine  waste  rock  with  a  maximum  <br />particle size of 3 inches as approved by MANAGER and CERTIFYING ENGINEER.  <br />  <br />