Newmont‐Cripple Creek & Victor Gold Mine  <br />Technical Specification No. 02200.DOCX  <br />Squaw Gulch VLF  <br />Project No.475.0106.006  <br />June 15, 2016  <br />  <br />  <br />  <br />Page 18  <br />3. CONTRACTOR shall place Drain Cover Fill in a single 24‐inch loose lift. The tracked  <br />equipment shall operate only over previously placed Drain Cover Fill. CONTRACTOR  <br />shall not operate equipment directly on geosynthetics. Only a dozer with a ground  <br />pressure not exceeding 8.7 psi can be used to place Drain Cover Fill. A CAT 12G  <br />motor grader, or equivalent approved by CERTIFYING ENGINEER, can be used for  <br />Drain Cover Fill final grading. Equipment used for placement will not be allowed to  <br />pivot on one track (i.e. no abrupt or sharp turns). There shall  be  no  downhill  <br />placement on slopes steeper than 4H:1V. Material can be placed along contours if  <br />buttressed from below.  Motor graders shall not be allowed to make abrupt turns,  <br />brake suddenly, or dig blade in which results in the tires spinning on the Drain  <br />Cover Fill surface.  <br />4. Highway compatible Rubber tired construction equipment shall not be allowed to  <br />travel  over  the  geomembrane  or  on  top  of  Solution  Collection  piping  unless  a  <br />thickness  of  at  least  45  inches  of  Drain  Cover  Fill  has  been  placed  over  the  <br />geomembrane and on  top of Solution Collection piping. The CONTRACTOR will be  <br />required to demonstrate to the MANAGER, DESIGN ENGINEER and CERTIFYING  <br />ENGINEER  that the equipment and procedures used are not detrimental to the  <br />geomembrane  and  piping,  at  no  cost  to CC&V.  Off  road  haul  truck  traffic  shall  <br />require a minimum of 60 inches for Cat 773 (or equivalent) of Drain Cover Fill  <br />placed over the geomembrane and  solution collection piping, and a minimum of  <br />120  inches  for  CAT  777  (or  equivalent)  of  Drain  Cover  Fill  placed  over  the  <br />geomembrane and solution collection piping.  <br />5. When placing Drain Cover Fill the maximum acceptable drop height is 3 feet.  <br />6. CONTRACTOR shall operate equipment in a manner that is protective of underlying  <br />geosynthetics. If MANAGER or CERTIFYING ENGINEER suspects the occurrence of  <br />any damage to the underlying geosynthetics, MANAGER will instruct CONTRACTOR  <br />to  remove  Drain  Cover  Fill  to  expose  the  geosynthetics. CONTRACTOR shall  <br />uncover,  repair  any  observed  damage  of  the  underlying  geosynthetics,  in  <br />accordance with the repair requirements of Sections 02776.0 and 02777.0 of these  <br />SPECIFICATIONS, and recover, at no cost to CC&V.  <br />7. CONTRACTOR shall place Drain Cover Fill at a rate such that the geomembrane liner  <br />is not exposed to ultraviolet light for more than 180 days.  <br />8. CONTRACTOR shall provide close continuous monitoring at the point of placement  <br />during the placement of the Drain Cover Fill over geosynthetics.  <br />9. CONTRACTOR shall  verify  the  final  thickness  of  Drain  Cover  Fill  to  determine  <br />compliance  with  this  SPECIFICATION. CONTRACTOR shall  record  verification  <br />location,  elevation,  and  thickness.    CQA  Monitor  shall  witness all  verification  <br />measurements. CONTRACTOR will submit a method of verifying Drain Cover Fill  <br />depth to MANAGER for approval. Grade markers shall be placed on a 50‐by‐50‐foot  <br />grid with additional points required for breaks in grade. CONTRACTOR shall remove