Laserfiche WebLink
I, <br />CRIPPLE CREEK & VICTOR GOLD MINING Co. <br />ANGLOGOLD ASHANTI (COLORADO) amec <br />SQUAW GULCH (VLF) WEEKLY REPORT foster <br />wheeler <br />Cat 740 haul trucks delivered Structural Fill material between stations 25+00 to 30+00 of the ADR <br />Haul Road. Cat dozers placed the Structural Fill upslope to the E Bench. Cat dozers also cut the <br />slope from station E14+0 to C16+50. A Cat smooth drum roller compacted the fill area. <br />A Cat smooth drum roller compacted subgrade between stations A10+00 to Al2+00. <br />CC&V hauled material to the Dump 4 surge in Phase 2 using Cat 793 haul trucks. A Cat D10 <br />placed the Structural Fill between stations N20+00 and N22+00. A Cat smooth drum roller <br />compacted the fill area. <br />Cat dozers finish graded slopes between stations DD6+00 to DD10+00 and DD15+00 to <br />DD18+00. <br />All of the above Structural Fill material was placed, compacted, and graded per the project plans <br />and specifications. <br />Subgrade: <br />Cat smooth drum rollers compacted subgrade per project specification below G4+00 to G8+00 <br />and E8+00 to E12+00. <br />Soil Liner Fill: <br />Cat dozers placed SLF above C Bench and above DD Bench. <br />A containment berm was constructed on the south perimeter between stations P4+00 and P8+00. <br />Cat dozers and a Cat roller finished and compacted the SLF surface upslope from stations A0+00 <br />to A10+00. <br />Drain Cover Fill: <br />None. <br />Underdrain System: <br />Primary Underdrain: Complete. <br />Secondary Underdrain: Structural Fill was placed above the secondary underdrain <br />between statons M10+00 and K16+00. <br />Tertiary Underdrain: Construction of several tertiary underdrains continued between <br />stations A15+00 and A20+00 and between stations C8+00 and <br />C12+00. Activity was in accordance with project plans and <br />specifications. <br />Leak Detection: <br />Approximately 25 LF of leak detection was removed to construct a tertiary underdrain from the <br />A14+00 to C11+00. Leak detection will be replaced following completion of the tertiary <br />underdrain. <br />