Laserfiche WebLink
ameO <br /> Unsuitable material from the former Highway 67 was removed from the subgrade upslope of <br /> Bench B stations BO+00 to B2+00 in the Phase 1 area. The material was replaced with structural <br /> fill per project specifications. <br /> Subgrade: <br /> Two dozers continued slope grading the subgrade downslope of Bench D stations DD4+00 to <br /> DD16+00 in the Phase 1 area while a Cat hammer hoe broke oversized rock in the subgrade <br /> surface. Portions of the subgrade in this area were compacted with a smooth drum roller <br /> Soil Liner Fill: <br /> Cat 777 haul trucks transported SLF from the Cameron stockpile to a location below Bench F <br /> stations FO+00 to F10+00 in the Phase 1 area on approved subgrade where it was stockpiled for <br /> future use. <br /> Low Volume Solution Collection Fill: <br /> The following low volume solution collection fill (LVSCF) areas in the PSSA were placed to <br /> finished grade per project specifications, inspected, and approved for primary geomembrane <br /> placement: <br /> i From the ADR haul road to Bench B between approximate stations B6+00 to B12+00. <br /> From Bench A to the PSSA floor between approximate stations A5+00 to A7+00. <br /> See the attached LVSCF map for all placement and accepted locations for primary geomembrane <br /> deployment. <br /> SLF Processing: <br /> Cameron Site: No SLF mining or processing occurred at the Cameron Site. However, Ames <br /> continued transporting the Cameron stockpiled SLF to a new stockpile located below Bench F <br /> stations FO+00 to F10+00 in the Phase 1 area. The processing equipment remains at the <br /> Cameron site. No new processing was performed during this reporting period. <br /> Underdrain System: <br /> Primary Underdrain: Complete. <br /> Secondary Underdrain: No work was performed during this reporting period. <br /> Tertiary Underdrain: Complete within the PSSA footprint. <br /> B) Underground Workings <br /> Confirmatory drilling occurred at underground workings#UG6200, UG#6429, #UG6313, and UG <br /> #6639. Additional remediation is required. <br /> A dozer and an excavator prepared working UG#6543 for geogrid placement. Further <br /> remediation is required. <br /> Geomembrane: <br /> PSSA <br /> Primary 100-mil DSMS LLDPE Liner Installation <br /> ECA installed 100-mil LLDPE smooth geomembrane at the west slope of PSSA from the ADR <br /> platform to the PSSA floor and south slope from the 9450-foot bench to the closure drain. Panels <br /> P-88 through P-143 were deployed on approved LVSCF. Seventeen full rolls and multiple partial <br /> rolls of 100-mil LLDPE smooth geomembrane were deployed yielding 6,967 lineal feet of fusion <br /> welds for an approximate installed weekly total of 131,400 square feet. Quality control was <br /> 2014 0906-MLE2 WEEKLY FINAL Page 2of <br />