Laserfiche WebLink
Estimated Powerline Removal Costs for Proposed Line from South Substation to Crusher <br /> Using Actual Costs at CCV for retiring power lines in the Phase V area of the AGVLF <br /> According to Marc Tidquist of CC&V this powerline project consists of 35 poles (personal communication MT 5-14-14) <br /> Based On 2010 Actual Costs for Retiring Power Lines for Amendment No.9 in VLF Phase V area. Information Provided by Mike Jahraus,Projects Manager <br /> for CC&V(2010 costs inflated to 2014$). <br /> Cost per pole in the VLF Phase V area= $ 489.28 Based on real-life costs in 2010 inflated to 2014 dollars-costs per pole. <br /> Grand Total Powerline Removal Cost= $ 17,125 <br /> $ 16,730 Reasonableness check <br /> Costs basis: Actual CC&V Experience on Removal of Phase 5 Powerline(2010);2014$=($458)x(1.0683 CPI Ratio)=$489.28 <br /> Reasonableness Check from Means 2014,p.36:$350 Poles+$128 Appputenances=$478 per pole <br /> MDE(5-14-14) <br />