Bowie No. 2 Mine C 1996083 Technical Revision No. 84- Second Adequacy Review Page 2 of 15 <br />additional information for the proposed revisions to depth and velocity and revise page 8 -29i to be <br />consistent with page EXH -8 -12, or restore the original values from the previously approved design. <br />7. BRL revised the reference and flow value on the table on page Exh -8 -29iii as requested, but the newly <br />revised page EXH -8 -31 indicates a minimum culvert size of 42" for Culvert H1. The design information on <br />page EXH -8 -168 indicates that a 30" pipe will be required, and BRL indicated in their response letter that a <br />42" pipe would be used. Please update the minimum size indicated on the table on page EXH -8 -31 <br />consistent with the design on page EXH -8 -168 and include a note that the 42" culvert will be installed. <br />8. Response accepted. BRL revise the reference on the table on page Exh -8 -29iii as requested. <br />9. Response accepted. BRL corrected the table on page Exh 8 -31 as requested. <br />10. Response accepted. BRL corrected the table on page Exh 8 -31 as requested. <br />11. Response accepted. BRL corrected the table on page Exh 8 -31 as requested. <br />12. a. Response accepted. BRL corrected the table on page Exh 8 -31 and provided design information for <br />Culvert C -G4, as requested. <br />b. During the initial adequacy review, we did not notice that Culvert C -1327 had been removed from the <br />table on page EXH -8 -31. The culvert is still shown on Maps 15 -1 and 21 -1, and should therefore remain <br />on this table. Please restore the information for Culvert C -827 on page EXH -8 -31. <br />c. The newly revised page EXH -8 -31 indicates a flow value of 0.00 for Ditch D -E1. Please restore the flow <br />value of 1.79 for Ditch E -1 on page EXH -8 -31. <br />13. Response accepted. BRL revised the calculations and flow values for Ditch H1 on page Exh 8 -166 as <br />requested. <br />14. BRL revised the Table of Contents for Volume XI as requested, but the stability analyses continue to be <br />listed under Appendix A. It is our understanding that Volume XI would be organized consistent with <br />Volume IX, and that the stability analyses would precede Appendix A, with the material balance <br />information occupying Appendix A. Please review the Table of Contents for Volumes IX and XI, and if BRL <br />intends to have Volumes IX and XI be consistent, revise the Volume XI table accordingly. <br />15. This item will be addressed under Technical Revision No. 77. <br />16. Response accepted. BRL revised Page 3 of Volume XI, as requested. <br />17. Response accepted. BRL revised the text to indicate a maximum pile height. Depending on the final <br />outcome of the stability analysis for the increased height and slope configuration, this maximum height <br />may again require revision. <br />18. Response accepted. BRL verified that pages 4a and 4b of Volume XI will be retained. <br />19. Response accepted. BRL corrected page 5 of Volume XI as requested. <br />CIRCES Cost Estimating Soffi are <br />