Cripple Creek & Victor Gold Mining Company <br />Cresson Project <br />Quality Assurance Monitoring and Test Results <br />Load Out Bin Relocation <br />July 7, 2009 <br />2.0 SUMMARY OF EARTHWORK CONSTRUCTION <br />Earthworks activities associated with the LOB relocation included the following: <br />■ Underground workings remediation, including excavation, confirmatory drilling, <br />installation of CSB; <br />■ Site grading, including cut /fill and blasting; <br />Im <br />■ SLF installation, placement and compaction, depth verification testing, and preparation <br />of SLF surface for geomembrane deployment; and <br />■ DCF placement above the upper geomembrane layer. <br />Ames generally used the following equipment during construction: <br />■ Bobcat S130 Skid -Steer Loader; <br />■ Caterpillar D6R Dozer (4); <br />■ Caterpillar D8R Dozer (3); <br />■ Caterpillar D9R Dozer; <br />■ Caterpillar D10T Dozer; <br />■ Caterpillar 966G Loader (4); <br />■ Caterpillar 988 Loader; <br />■ Water Trucks (2); <br />■ Caterpillar 773 Water Wagon; <br />■ Caterpillar 14G Motor - Grader; <br />■ Caterpillar 140H Motor - Grader; <br />■ Caterpillar CS563 Compactors (2); <br />■ Caterpillar 320 Trackhoe; <br />■ Caterpillar 345 Trackhoe; <br />S: \PROJECTS \1125E CCV CQA \H3 - CONSTRUCTION \LOB CERT REPORT\REPORT BODY\LOB CERT REPORT 2009.07.01.DOC 5 <br />