amee- <br />Clay (SLF) Processing_ <br />Cameron Site: Clay processing continued during this reporting period. <br />Squaw Gulch Clay Borrow Site: Overburden removal occurred during this reporting period. <br />Underdrain System: <br />Secondary Underdrain: Installed between the Ball Mill fill and Dump No.4 In addition installation occurred at <br />Station 46+00 below the ADR haul road. <br />Approximate total of 1580 feet of Secondary underdrain has been completed. <br />Primary Underdrain: No work was performed on the Primary underdrain during this reporting period. <br />A total of 1280 feet of Primary underdrain has been completed. <br />Temporary Underdrain: No work was performed on the temporary underdrain during this reporting period. <br />Tree /Slash Clearing, Chipping_ <br />Seed Masters paused operations until further notice. <br />B) Underground Worl ings <br />Confirmatory drilling was performed on underground working No. 6011, No. 6062. All drill hole locations were <br />established on a 4 -foot center isolating any voids found. Further remediation efforts will be ongoing until remediated. <br />Summary of the remediation efforts will follow 100% remediation. <br />Blasted rock was excavated and removed from UG Working No, 6167 and No.U6273. Materials removed were used <br />as fill. 191 cubic yards of concreted was placed in UG U6273 <br />Anaconda Mine: Blasting occurred on 10.3.13. Loose materials were scaled and pushed from the sides as <br />remediation efforts continue. <br />Q Highway 67 <br />Topsoil material was spread over the slope within the natural gas line right -of -way, in addition to portions of the <br />slope above the south MSE wall were covered as -well, <br />Subgrade was graded and proof rolled for Class 6 (ABC) material placement. <br />Class 6 (ABC) materials was placed on the victor (South) side of the realignment at Sta. 1027 +50 to Sta. 1031 +50 <br />in preparation of pavement tie -in. <br />Ditch grading occurred and connected to the culvert near Sta 1021+00 <br />An inlet located at Sta, 1028+03 was excavated and filled with slurry, <br />Topsoil placement on downstream slope was completed during this reporting period. <br />South MSE Wall: <br />No progress occurred during this reporting period, Progress is waiting on leveling mat construction and timber <br />connection placement. <br />Page 2 of 6 NILE2 WE 10.05.13.doc <br />