Laserfiche WebLink
<br />L. M, ALEXANDER <br /> <br />Slide 5 4. The site must be within economical transmissiQn distances from major load centers, If other <br />transmission facilities are nearby and can be interconIj.ected, this is a plus factor in the plant site <br />selection, <br /> <br />Now, there is a 5th critical item entering into the powerplant siting consideration-sometimes <br />more important than the others, as Jack Moore will so well point out-the social or environmental <br />considerations. <br /> <br />Slide 6 Based on our studies of the Navajo site near Page, we felt that it optimized all of these con, <br />siderations, So late in 1967 we placed on order three 750,000 KW turbine generators, In January <br />1968, Western utilities met in phoenix for preliminary discussions on the Navajo Plant. <br /> <br />Spring of 1968 saw the Central Arizona Project moving through Congress shorn of its hydro- <br />electric pumpers and cash registers (Bridge and Marble hydroelectric projects) and with a pumping <br />power need of 400,000 to 600,000 KW, <br /> <br />"i <br /> <br />Secretary of the Interior Udall '" June of 1968 :called a meeting among Southwestern utilities <br />and the Navajo Tribe. The Secretary asked that the p,ower resource studies being conducted by the <br />utilities on the Navajo Project be expanded to includ~ the pumping needs of CAP. The reason the <br />Slide 7 Secretary desired participation in the proposed Navaj~ plant is easily seen in this slide which shows <br />that the annual savings to the Central Arizona Project from "participation" rather than purchasing <br />pumping power is in the order of $10 million per year-this would be an added cost to CAP water <br />users, <br /> <br /> <br />A Steering Committee was set up to determine the most economical way of supplying CAP <br />requirements, and the area's power requirements for the 1973,76 period, and I was elected chairman. <br />The Steering Committee then coordinated the Wor~ of ten task forces formed to work out and <br />Slide 8 analyze the project in depth, This was accomplished with what I believe to be the greatest array of <br />talent ever applied to a single power resource project, <br /> <br />Complete start,overs were necessary when New Mexico and El Paso decided on another site, <br />and again in the Spring of 1969 when Southern California Edison pulled out of the project. These <br />actions cut to half the optimum size of the project which had been found by the task forces to be <br />five million KW-2500 MW at Navajo and 2500 MW at the existing Four Corners site. <br />I <br /> <br />Instead of six 820,000 KW units we finally settled on three 770 MW units having a total <br />capacity of 2310 MW. <br /> <br />The balance of 1969 was primarily intensive work and negotiation among the respective task <br />forces on details of the various agreements. At times, I for one, often wondered if we were ever <br />going to pull the loose ends together. The negotiati<;>ns were often frustrating, long drawn out, and <br />about as complicated as power negotiations could p'ossibly be, The trouble was that it wasn't just <br />power negotiations. Seemingly everybody in the whole Colorado Basin got in the act. Nevertheless, <br />by September of 1969, all of the remaining particip~nts were ready to recommend to their manage, <br />Slide 9 ment, execution of the various agreements and arrangements-which they have proceeded to do, <br />This slide shows the participant's share of the plant, <br /> <br />Because of the critical peak demands anticipated in the summer of 1974, it is important that <br />construction contracts be entered into during December 1969. We expect to award such a contract <br />early next month. The second and third units are scheduled for operation in 1975,76, as you can <br /> <br />,24, <br />