<br />1 DIVERSION STRUCTURE CONSTRUCTION
<br /> COST ESTIMATE
<br />1 REFERENDUM A
<br />1 ITEM QUANTITY UNIT PRICE AMOUNT
<br /> H-PILING 6000 LF 25,00 150,000,00
<br />1 1422 LF 20,00 28,440,00
<br /> SHEET PILING 812xl5 SF 6,50 79,170,00
<br />1 384x20 SF 6,50 49,920.00
<br /> 180xl2 SF 6,50 14,040,00
<br />I CONCRETE 540 CY 280,00 151,200,00
<br /> REBAR 82,000 LB 0,50 41,000,00
<br />1 BRIDGE UNITS 2 EA 5000,00 10,000,00
<br />1 CHANNEL EXCA V, 8,000 CY 5,00 40,000,00
<br />1 RIP-RAP 1530 CY 8,00 12,240,00
<br />RADIAL GATE 1 EA 16,000,00 16,000,00
<br />1 RAILING 330 LF 18,00 5,940,00
<br />1 EQUIPMENT ROOM 1 EA 4,700,00 4,700,00
<br /> 30 FT, OBERMEYER GATE 2 EA 32,600,00 65,200,00
<br />1 CONTROLS 1 LS 8,000,00 8,000,00
<br />I COMPRESSOR 1 EA 4,300,00 4,300,00
<br /> CONST, SURVEY 1 LS 3,300,00 3,300,00
<br />I MOBILIZATION 1 LS 18,000,00 18,000,00
<br />1 CONSTRUCTION COST 701,450,00
<br />I ENGINEERING FEE 49,100,00
<br /> 5% CONTINGENCY 35,080,00
<br />1 TOTAL PROJECT COST $ 785,630,00