<br />I
<br />1
<br />I DIVERSION STRUCTURE CONSTRUCTION
<br /> COST ESTIMATE
<br /> REFERENDUM B
<br />1
<br /> ITEM QUANTITY UNIT PRICE AMOUNT
<br />1 H-PILING 6000 LF 25,00 150,000,00
<br />1 SHEET PILING 812x15 SF 6,50 79,170,00
<br />I CONCRETE 540 CY 280,00 151,200,00
<br />REBAR 82,000 LB 0,50 41,000,00
<br />I BRIDGE UNITS 2 EA 5000.00 10,000,00
<br />I CHANNEL EXCAV, 8,000 CY 5,00 40,000,00
<br /> RIP-RAP 300 CY 8,00 2,400,00
<br />1 RADIAL GATE 1 EA 16,000,00 16,000,00
<br />1 RAILING 330 LF 18,00 5,940,00
<br /> EQUIPMENT ROOM 1 EA 4,700,00 4,700,00
<br />1 30 FT, OBERMEYER GATE 2 EA 32,600,00 65,200,00
<br />1 CONTROLS 1 LS 8,000,00 8,000,00
<br /> COMPRESSOR 1 EA 4,300,00 4,300,00
<br />1
<br />CONST, SURVEY 1 LS 3,300,00 3,300,00
<br />I MOBILIZATION 1 LS 18,000.00 18,000,00
<br />I CONSTRUCTION COST 599,210,00
<br /> ENGINEERING FEE 49,100.00
<br />1 5% CONTINGENCY 32,315.00
<br />I TOTAL PROJECT COST $ 680,625,00