TABLE 1
<br /> RIO GRANDE RESERVOIR-SLOPE LINER AND CURTAIN
<br /> MCMS,INC.BID PRICE FOR SUMMER 2013 WORK
<br /> Item Description Quantity Unit Bid Unit Cost Total
<br /> 1 Mobilization 1 LS $ 50,500.00 $ 50,500.00
<br /> 2 Clay Liner and Freeboard Dike
<br /> a Excavation 24,000 CY $ 6.00 $ 144,000.00
<br /> b&c Zone 1 (3"minus)Stockpiled and Additional 17,000 CY $ 8.50 $ 144,500.00
<br /> d Zone 2(6"minus) 39,000 CY $ 10.00 $ 390,000.00
<br /> e Random Fill 4,300 CY $ 4.50 $ 19,350.00
<br /> f Zone 3(3'-6") 2,800 CY $ 8.50 $ 23,800.00
<br /> g Riprap 5,000 CY $ 7.00 $ 35,000.00
<br /> h Crest Road and Turnaround 550 LF $ 8.00 $ 4,400.00
<br /> i Coffer Dam 1 LS $ 9,800.00 $ 9,800.00
<br /> j Remove,Stockpile and Respread Existing Riprap and 1,400 CY $ 6.00
<br /> Bedding $ 8,400.00
<br /> k Blasting 1 LS $ 15,000.00 $ 15,000.00
<br /> I Guard Rail Rirap, Erosion Control and Survey 1 LS $ 24,500.00 $ 24,500.00
<br /> Subtotal $ 818,750.00
<br /> 3 Mobilization/Demobilization for Grout Curtain 1 LS $ 31,150.00 $ 31,150.00
<br /> 4 Dual Liner Grout Curtain
<br /> a Primary Holes
<br /> a.i Rotary Duplex Drilling 1,210 LF $ 57.75 $ 69,877.50
<br /> Air Rotary Drilling(Rock) 2,470 LF $ 39.00 $ 96,330.00
<br /> a.ii Hookups 104 EA $ 420.00 $ 43,680.00
<br /> a.iii Sacks of Cement 4,000 EA $ 31.50 $ 126,000.00
<br /> b Secondary Holes
<br /> b.i Rotary Duplex Drilling 625 LF $ 57.75 $ 36,093.75
<br /> Air Rotary Drilling(Rock) 1,210 LF $ 39.00 $ 47,190.00
<br /> b.ii Hookups 52 EA $ 420.00 $ 21,840.00
<br /> b.iii Sacks of Cement 1,600 EA $ 31.50 $ 50,400.00
<br /> Foundation Grout Repair 5 EA $ 700.00 $ 3,500.00
<br /> Water Pressure Test 120 HRS $ 600.00 $ 72,000.00
<br /> c Core Borings(3 holes) 300 LF $ 85.00 $ 25,500.00
<br /> Subtotal $ 592,411.25
<br /> General Contractor Grout Curtain Items
<br /> (Drill Cutting and Water Control) 1 LS $ 53,175.00 $ 53,175.00
<br /> 5 Clay Blanket
<br /> a Zone 1 (3"minus) 1,600 CY $ 10.00 $ 16,000.00
<br /> b Cover Soil 1,920 CY $ 4.50 $ 8,640.00
<br /> c Grout Curtain Temporary Road Excavation 2,720 CY $ 6.00 $ 16,320.00
<br /> d Riprap 800 CY $ 7.00 $ 5,600.00
<br /> e Riprap Bedding 400 CY $ 8.50 $ 3,400.00
<br /> Subtotal $ 49,960.00
<br /> 6 Miscellaneous
<br /> a Seeding and Fertilizing 10 AC $ 3,150.00 $ 31,500.00
<br /> b Repair Staff Gage 1 LS $ 8,400.00 $ 8,400.00
<br /> c Replenish Existing Dam Riprap 4,200 CY $ 7.00 $ 29,400.00
<br /> d Dam Monitoring Points 8 EA $ 175.00 $ 1,400.00
<br /> e Permanent Monument Poings 3 EA $ 290.00 $ 870.00
<br /> f Quality Control Testing 1 LS $ 22,000.00 $ 22,000.00
<br /> g Office Trailer and 2 Porta Johns 1 LS $ 15,500.00 $ 15,500.00
<br /> Subtotal $ 109,070.00
<br />
|