The infrastructure cost estimate for “Alternative No. 1 (Greeley No. 2 Canal Delivery)” is <br />$1,345,131. <br />Table 14 - Infrastructure Cost Estimate –Greeley No. 2 Canal Delivery <br />ItemNo. Description Estimated Quantity Unit Unit Price Cost <br />1Replace and Enlarge Existing Ditch 6,000 LF $25$150,000 <br />2Replace Headgateat Greeley No. 2 Ditch 1EA $ 16,000 <br />$6,000 <br />3Furnish and Install 24 Inch PVC Pipe 2,300 LF $345,000 <br />$150 <br />1 <br />4Pump Station (10 CFS) 68HP <br />$2,657$180,676 <br />2 <br />5Miscellaneous Site Work 1LS <br />$75,000$75,000 <br />3 <br />6Access Road 4,300 LF $20$86,000 <br />7Dewatering 30Days <br />$1,000$30,000 <br />8Outlet Flow Measurement Structure 1LS <br />$45,000$45,000 <br />Total <br />$927,676 <br /> <br />Mobilization 5% <br />$46,384 <br /> <br />Engineering (Designand Construction Observation) 10% <br />$92,768 <br />Permitting 10% <br />$92,768 <br />Contingency 20% <br />$185,535 <br /> <br />Total <br />$1,345,131 <br />Notes: <br />1Raw water pump station assuming 60% pump efficiency and does not include the cost of electrical service <br /> to the pump station. <br />? <br />2Miscellaneous site work includes revegetation, final grading, and miscellaneous riprap. <br />3Access Roads: $20/LF for moderate terrain and includes clearing, grubbing, grading, and road base. <br />The cost estimate for “Alternative No. 2 (Cache la Poudre River Pump Station) is <br />$2,156,284. However, there are some overlapping costs between Alternative No. 1 and <br />Table 16 <br />No. 2. is a combination of Alternatives No. 1 and No. 2 with a reduction for <br />Table 16 <br />these overlapping costs. itemizes the total infrastructure cost ($2,515,004) <br />Table 13 <br />presented in the final cost listed in . <br /> <br />