Laserfiche WebLink
<br />. <br /> <br />. <br /> <br />Hyd ro Faci lit i es <br />As it would not be realistic to construct Sheephorn Dam without <br />hydro power facilities, the cost or the hydro plant and related works <br />was made independent of the dam costs. The power facilities estimated <br />costs are as follows: <br /> <br />TAB LE 5 <br />SHEEPHORN POWERHOUSE CONSTRUCTION COSTS <br />(Costs expressed in thousands of dollars) <br /> <br />Powerhouse (23 MW) <br />Transmission Facilities <br />Reregulation Dam <br /> <br />. <br /> <br />Tota I <br /> <br />~18,500 <br />3,300 <br />2.500 <br /> <br />$24,300 <br /> <br />$ 2,700 <br />5,300 <br /> <br />32,300 <br /> <br />$30,000 <br /> <br />Subtotal <br /> <br />Indirect Construction Costs <br />Conti ngenci es <br /> <br />Round to <br /> <br />From the foregoing, the total estimated 1980 cost of the project, <br />including power facilities is $170,000,000. <br /> <br />~ <br /> <br />-16- <br />