Laserfiche WebLink
<br /> <br />COLORADO RIVER STORAGE PROJECT <br /> <br />21 <br /> <br />site was progressing well ahead of schedule at the close of the fiscal <br />year. <br /> <br />GLEN CANYON STORAGE UNIT; ARIZONA <br /> <br />Work on the prime contract for construction of the 700-foot-high <br />concrete arch d$m and the 900,000ckilowatt powerplant was at a <br />virtual standstill from July 6, 1959, to January 4, 1960, due to a <br />general strike of the contractor's employees. Construction progress <br />at June 30 1960, was behind schedule, with 38 percent aggregate <br />work compfetion in 45 percent of the overall contract time. By the <br />end of the fiscal year, the excavation for the dam and powerplant <br />foundation and keyways was completed, and placement of concrete <br />in both structures was initiated in June 1960. <br />Other major construction items completed during the fiscal year <br />were the administration building; garage, fire station, and police build- <br />ings; seismograph vault; and soil stabilization in the town of Page, <br />Ariz. <br />Various items of equipment for installation in the dam and power- <br />plant, such as pen$tocks and outlet pipes, radial gates and gate hoists, <br />turbines, and cranes, were in the process of manufacture and fabrica- <br />tion at the close of, the fiscal year. <br /> <br />NAVAJO UNIT, N;EJW MEXICO <br /> <br />At June 30, 1960, progress by the prime contractor for construction <br />of the 405-foot-high earth and rock fill dam on the San Juan River <br />in the northwestern part of New Mexico was well ahead of schedule, <br />with 58 percent of 'work performed in 42 percent of the time allowed <br />by the contract. Diversion of the river through the main outlet- <br />works tunnel was accomplished and some 12 million cubic yards of <br />fill material had been placed in the dam by the end of the fiscal year. <br />~ Equipment items such as outlet gate valve, outlet pipe, steel walk- <br />way, and intalre bulkhead and embedded metalwork for the intake <br />structure of the outlet works were in the process of manufacture and <br />fabrication. <br /> <br />TRANSMISSION DIVISION <br /> <br />During fiscal year 1960, further studies were made on the overall <br />plan for the power'transmission system within the Upper Colorado <br />River Basin. Meetings were held with prospective preference cus- <br />tomers and private 'utility groups for the purpose of discussing and <br />resolving technical problems relative to the location of lines and <br />operating characteristics of the transmission system. <br />In response to a presentation of a tentative proposal for transmission <br />lines, there was received by the Bureau of Reclamation on October 1, <br />1959, a plan from si~ electric companies under which they would con- <br />struct certain elements of the transmission system. The utilities, in <br />April 1960, quoted 1fheeling charges applicable under the foregoing <br />proposal. , <br />The Bureau devised a possible all-Federal tran~mission system "S <br />the basis for establishment of rate schedules for project power and as a <br />yardstick to evaluate the proposal of the utility companies. The <br />Secretary of the Intehor approved this yardstick system on May 17, <br />1960. At the same time he also approved the area within which the <br />power would be marketed and the broad criteria under which it would <br />be marketed. On the basis of these approved criteria, compilation of <br /> <br />