, TW_1 <br />In addition to the structural fill placement for the PSSA toe berm embankment, the contractor continued cut to fill <br />operations and compaction by method specification located at the mid -way ADR haul road location at approximate <br />Sta.44 +00 — 47 +00. A Cat D8 Dozer with GPS and a Cat C556 Smooth Drum roller was utilized. Progress is <br />expected to continue. <br />See Hwy 67 below for detail of embankment fill progress. <br />Note: An Amec field representative monitored structural fill material temperatures placed within the areas of fill <br />during all shifts. Average structural fill temperatures were above 327 <br />Clay (SLFl Processing: <br />Cameron Site: No clay mining or processing occurred during this reporting period due to a saturated site from <br />previous rains. However on July 31St an Amec representative potholed 17 test pit's to determine possible clay limits <br />within an area of the Whex, adjacent the Cameron site. A sample was taken from each pit and returned to our <br />laboratory for classification and permeability testing. Results will be forwarded upon completion. <br />Squaw Gulch Site: <br />No work occurred at the VLF clay borrow site during this reporting period. <br />Underdrain System: <br />Secondary Underdrain: No work was performed on the Secondary underdrain during this reporting period. <br />A total of 1380 feet of Secondary underdrain has been completed. <br />Primary Underdrain: No work was performed on the Primary underdrain during this reporting period. <br />A total of 1280 feet of Primary underdrain has been completed. <br />Temporary Underdrain: Temporary underdrain pipe is installed thru the embankment. No other work occurred <br />during this reporting period. <br />Tree /Slash Clearing, Chipping: <br />Seed Masters paused operations until further notice. <br />B) Underground Workings <br />Confirmatory drilling was not performed during this reporting period.. <br />During this reporting period exploratory excavation was performed on UG working No. U6122, No. U6255, No. <br />6260 and No. U6263. Site's listed require further investigation and excavation into bedrock as remediation <br />continues to be completed. <br />It should be noted, working No.U6263 is planned to have a concrete Mug and cemented rock fill for remediation. Its <br />expected remediation on this working will be completed during the next reporting period. <br />During this reporting period remediation efforts were performed and completed on UG working No.6079, No. 6084, <br />No. 6196, No. 6206, No. 6251, No. 6252, No, 6253, No. 6254, No. 6255, No . 6259, No. 6264, No. 6265 and No. <br />U6267. Sites listed were excavated to practical refusal into rock varying depths depending on the working <br />remediated. The site for each working was then backfilled in 2 foot loose lifts to approximate planned subgrade <br />elevation using the onsite structural fill (excavated material) and "bucket tamped" with the back of the CAT 330 <br />excavator bucket. All backfill material was free of organic material, ice and snow and are considered remediated <br />as specified. <br />Page 2 of 6 MLE2 WE 08.03.13.doc <br />