Time frame <br />Area & Location <br />Sequence <br />2012 - 2017 <br />Final highwall bench configuration <br />along West boundary with BLM <br />2012 — 2015 southern <br />1/3 of BLM lease area <br />2015 — 2017 centerl /3 <br />of BLM lease area <br />2017 - 2037 <br />Highwall mining to new West permit <br />boundary <br />Highwall progression <br />north and west <br />2037 — 2057 <br />Highwall mining to northwest limit <br />Final highwall <br />configuration <br />2057 - 2077 <br />Final pit floor elevation attained <br />2077 - 2082 <br />Main pit area topsoil /plant medium <br />hauled to main pit area, revegetation <br />of main pit area begins <br />Pit floor revegetation <br />initiated at southern end <br />of lower pit, then <br />moving northward <br />and <br />4 <br />the out slopes of the sediment ponds; grading within the final pit configuration areas will be no more <br />than 3:1. Slopes in the highwall areas will be 0.25:1 <br />(d) Where applicable, plans for topsoil segregation, preservation, and replacement; for <br />stabilization, compaction, and grading of spoil; and for revegetation. The revegetation plan shall <br />contain a list of the preferred species of grass, legumes, forbs, shrubs or trees to be planted, the <br />method and rates of seeding and planting, the estimated availability of viable seeds in sufficient <br />quantities of the species proposed to be used, and the proposed time of seeding and planting; <br />There is no topsoil incurred at the surface of this mining operation. Topsoiling of the final pit floor <br />will be accomplished with fines materials produced from crushing and screening operations or will <br />be imported from other sites. If topsoil is "mined" from neighboring land owned by the mine <br />operator, a plan for removal and revegetation of the borrow area will be submitted to the Division for <br />approval prior to disturbance. Revegetation details such as species, fertilizer rates, times, etc., can be <br />found below. <br />(e) A plan or schedule indicating how and when reclamation will be implemented. Such plan or <br />schedule shall not be tied to any specific date but shall be tied to implementation or completion of <br />different stages of the mining operation as described in Subparagraph 6.4.4(1)(e). The plan or <br />schedule shall include: <br />(i) An estimate of the periods of time which will be required for the various stages or phases of <br />reclamation; <br />(ii) A description of the size and location of each area to be reclaimed during each phase; <br />(iii) An outline of the sequence in which each stage or phase of reclamation will be <br />carried out. (The schedule need not be separate and distinct from the Reclamation Plan, <br />but may be incorporated therein.) <br />RECLAMATION SCHEDULE AS INTEGRATED WITH THE MINING PLAN <br />(f) A description of each of the following: <br />(i) Final grading - specify maximum anticipated slope gradient or expected ranges <br />thereof; <br />