PART 2.0 DESCRIPTION OF PARTIES TO CONSTRUCTION QUALITY ASSURANCE <br />SECTION 01400.2 GEOSYNTHETIC CONSTRUCTION QUALITY ASSURANCE (CQA) PLAN <br />PART 1: INTRODUCTION <br />ame0 <br />This plan addresses the construction quality assurance (CQA) procedures for the installation of the <br />geosynthetic components used for the construction of the Process Solution Enhancement System (PSES) <br />Project, Teller County, Colorado. This program has been developed to assure that the construction of the <br />geosynthetic components are in compliance with the project SPECIFICATIONS and to demonstrate that <br />the regulatory requirements for the construction are achieved. <br />The objective of this plan is to assure that proper materials, construction techniques, and procedures are <br />followed by the CONTRACTOR and that the intent of the design is met. This program also intends to <br />identify problems that may occur during construction and provide the means for resolution of these <br />problems. <br />This program addresses quality assurance, not quality control. This CQA Plan is independent of the <br />quality control (QC) programs conducted by the MANUFACTURERS, INSTALLERs, and <br />CONTRACTORS. The intent of the CQA Plan is to provide independent third party verification and <br />testing, to demonstrate that the INSTALLER and CONTRACTORS have met their obligations in the <br />supply and installation of geosynthetic materials according to the design, project SPECIFICATIONS, <br />contractual and regulatory requirements. Quality control is provided by the MANUFACTURERS, <br />INSTALLERS, and CONTRACTORS and refers to those actions taken by them to ensure that their <br />materials and workmanship meet the requirements of the plans and project SPECIFICATIONS. <br />The following section provides descriptions of the parties to this CQA plan including their responsibilities <br />and qualifications. <br />2.01 CC &V: <br />In this CQA Plan CC &V refers specifically to Cripple Creek & Victor Gold Mining Company. CC &V <br />owns and operates site and PSES. <br />2.02 MANAGER: <br />In this CQA Plan the MANAGER refers specifically to the individual appointed by the Cripple Creek & <br />Victor Gold Mining Company. The MANAGER is the official representative of CC &V responsible for <br />all construction activities including oversight and direction during construction. The MANAGER is also <br />responsible for coordinating construction and CQA activities for the project. <br />The MANAGER shall serve as communications coordinator for the project initiating preconstruction and <br />resolution meetings. As communications coordinator, the MANAGER shall serve as a liaison between all <br />parties involved in the project to ensure that ongoing communications are maintained. The MANAGER <br />and CERTIFYING ENGINEER shall also be responsible for the resolution of all CQA issues that arise <br />during the installation of the geosynthetics. <br />Duties for this position include the following: <br />• review and approval of design DRAWINGS and project SPECIFICATIONS for all <br />geosynthetic components of the PSES earthworks project; <br />Section 01400.2 Page 1 of 11 <br />Geosynthetic CQA Plan <br />June 19, 2012 <br />Revision 1 <br />