ameO <br />PROCESS SOLUTION ENHANCEMENT SYSTEM FIELD MONITORING SUMMARY <br />(WEEKLY REPORT) <br />Project Title: CC &V/ PSES <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Process Solution Enhancement System <br />Date: May 12, 2012 <br />Reporting Period: 516/2012 through 5/12/2012 <br />Days <br />S <br />M <br />T <br />W <br />T <br />F <br />S <br />Work Shifts <br />D <br />D <br />D <br />- <br />D = Day Shift N = Night Shift <br />Project No.: 74201125KO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Ambient Temperature Range (F): Low: 24 °F to 36 °F ( + / -) High: 33 °F to 63 °F <br />AMEC CQA: Personnel On -site through the Reporting Period (See Attachment A). <br />AMES /Lonestar: Work activities were paused at the beginning of the week due to saturated work <br />surfaces. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />I) Process Solution Enhancement System (PSES) <br />A) Subgrade Preparation <br />No work performed during the shifts. <br />B) Soil Liner Fill (SLF) <br />Soil liner fill (SLF) was hauled from the South Cresson clay stockpile using CAT 40 -ton <br />articulating haul trucks loaded by a CAT 988 front -end loader. Placement was performed using <br />two CAT D -6 dozers in a one -foot compacted lift. Subgrade was approved and moisture <br />conditioned prior to placement using a tandem -axle water truck. Moisture conditioning of SLF <br />material was performed in place using a tandem -axle water truck and compaction was achieved <br />using a 10 -ton vibratory smooth drum compactor. Nuclear density testing, moisture verification, <br />and depth check testing was performed with results within project specifications. Test locations <br />were surveyed by Ames. <br />PSES Weekly Report WE 05.12.2012 <br />