Laserfiche WebLink
Table E -1: <br />Task # Description Time Needed (Months) <br />1 Strip topsoil and place berm along north side of Pit 1 0.5 <br />2 Strip overburden from Pit 1 to stockpile at southeast corner of site 0.5 <br />3 Bring in portable crusher, screen plant, stackers, truck scale, and scale house. 0.25 <br />4 Mine Pit 1 144.0 <br />5 Reclaim Pit 1 and mine Pit 2 48.0 <br />6 Reclaim Pit 2 and mine Pit 3 24.0 <br />7 Reclaim Pit 3 12.00 <br />8 Remove all facilities 0.50 <br />9 Reseed and mulch reclaimed areas 0.25 <br />Total months <br />Total years <br />230.5 <br />19.2 <br />Note that Task 7 includes the removal of the visual berm by bulldozing this topsoil onto the <br />backfilled slopes for final reclamation. The ramp from the 33 Road access to the pit bottom will <br />be left in place as a mild shelf, which could be used to allow boats to enter the lake. <br />This schedule is planned to minimize disturbance by reclaiming areas as additional mining is <br />undertaken. Note: If large contracts are awarded to the site, production could increase to the <br />permit maximum, thereby curtailing the life of the pit. On the other hand, if contracts are less <br />than anticipated, the life of the pit could be extended. This table is based on a reasonable <br />projection of average production rates. <br />Otter Creek Pit December 12 E - <br />