2. Topsoil replacement <br />Initial stripping of topsoil in Pit 1 will be used to partially construct the perimeter berm for a <br />visual barrier on the north sides of the project. Due to the expected volumes, overburden <br />stripped from Pit 1 will have to be stockpiled directly south of Pit 1 in the designated stockpile <br />area. <br />Topsoil stripped from the latter portions of Pit 1 and all of Pit 2 will be used to extend the visual <br />berm along the entire west edge of the pit, as shown on Map C -2. Topsoil from Pit 3 will be used <br />to cover portions of the backfilled slope of Pit 1. <br />Once all overburden has been placed in its final location, the visual berm will be removed to <br />cover all backfilled slopes with the required topsoil. <br />3. Haul Roads and Access <br />It is planned that the haul road utilized in the mining process will remain as an access road for <br />the south and east sides of the site. An additional access road will be created by refilling the area <br />currently known as the Oberding Drain. This will provide access from the west side (32 1/2 <br />Road) to the southeast (haul road) and create an earth fill separating the three -pit excavation into <br />two lakes. All areas will be topsoiled, seeded and mulched. <br />4. Reclamation Timetable <br />Listed below is the proposed reclamation timetable, which is essentially the same as the mining <br />timetable presented in Exhibit D. <br />Otter Creek Pit December 12 E -2 <br />