2. Mining Timetable <br />The following timetable is a best estimate of the sequence of operations for the life of the mine <br />for the 3 Pits assuming the anticipated annual average of 100,000 tons per year sold from Pit 1 <br />and 250,000 tons per year for Pit 2 and 425,000 tons per year for 3. <br />Table D-4 <br />Task # Description Time Needed (Months) <br />1 Strip topsoil and place berm along north side of Pit 1 0.5 <br />2 Strip overburden from Pit 1 to stockpile at southeast corner of site 0.5 <br />3 Bring in portable crusher, screen plant, stackers, truck scale, and scale house. 0.25 <br />4 Mine Pit 1 144.0 <br />5 Reclaim Pit 1 and mine Pit 2 48.0 <br />6 Reclaim Pit 2 and mine Pit 3 24.0 <br />7 Reclaim Pit 3 12.00 <br />8 Remove all facilities 0.50 <br />9 Reseed and mulch reclaimed areas 0.25 <br />Total months <br />Total years <br />230.5 <br />19.2 <br />Note that Task 7 includes the removal of the visual berm by bulldozing this topsoil onto the <br />backfilled slopes for final reclamation. The mining schedule is planned to minimize disturbance <br />by reclaiming areas as additional mining is undertaken. Note: If large contracts are awarded to <br />the site, production could increase to the permit maximum, thereby curtailing the life of the pit. <br />On the other hand, if contracts are less than anticipated, the life of the pit could be extended. This <br />table is based on a reasonable projection of average production rates. <br />Otter Creek Pit December 12 D - <br />