amet-1 <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed DCF placement within the Mill Site Earthworks project, including ambient and fill <br />temperature monitoring when necessary. <br />AMEC observed overburden fill placement for the Mill Site Earthworks project, including ambient and fill <br />temperature monitoring when necessary. <br />AMEC observed construction of MSE Wall's #3 and #4. <br />MEW Weekly Report WE 11.24.2012.docx <br />