Mike Boulay <br />-18- October 16, 2012 <br />37. On Figure 2.2 -5, the naming of the haul roads is inconsistent with the application <br />text. Please rename the Portal Haul Road "Haul Road #1" and the Gob Pile <br />Haul Road "Haul Road #2 ". <br />MCM: Please see revised Figure 2.2 -5. Haul Road #2 is now approximately 65' long <br />and has a zero grade, so a profile is not included. <br />38 Figure 2.2 -5 provides cross sections for three specific stations for Haul Road #1. <br />Please revise this map to also include cross sections for Haul Road #2 at <br />approximate stations 6 +00, 13 +50 and 21 +00. <br />MCM: No longer applicable, haul road #2 as initially submitted has been removed from <br />consideration. Haul Road #1 is an existing road. A typical section is shown on <br />Figure 2.2 -5. <br />39. Access Road #1 is described at the top of page 2.05 -18. The description <br />includes length and grade, but the width is not given. Please revise the <br />description to give the width of proposed Access Road #1. <br />MCM: No longer applicable, access road #2 as initially submitted has been removed <br />from consideration. There are no longer access roads planned on -site. <br />40. No plans and drawings specific to Access Road #1 have been submitted, as <br />required by 2.05.2(3)(c)(vii). Please provide plan and profile information for <br />the access road which demonstrates that the design criteria of 4.03.2 have <br />been met. <br />MCM: No longer applicable, access road #2 as initially submitted has been removed <br />from consideration.. <br />41. Page 2.05 -16 describes the Design and Construction of roads on the site. The <br />third paragraph of the section addresses embankment specifications for road <br />sections not within the disturbed area in accordance with Rule 4.05.2(4). Please <br />provide a description of (or illustrate graphically on Figure 2.2 -5 Haul Road <br />Plan and Profile) the specific road segments to which these specifications <br />will be applied. <br />MCM: At this time, there are no haul roads for mine operations that are not in the <br />disturbed area, however, the Operator sees no harm leaving the text in place. <br />Rule 2.05.3(4) Ponds, Impoundments, and Diversions <br />