• <br />C) Slope Contouring <br />No work performed during the week. <br />D) Soil Liner Fill (SLF) <br />Soil liner fill (SLF) placement was performed in the areas shown on Figure 3. Subgrade was <br />approved and moisture conditioned prior to placement using a tandem -axle water truck. <br />Placement was performed using various CAT dozers and a John Deere 120 excavator in a one - <br />foot compacted lift. SLF material was hauled to the Mill Platform from the temporary SLF stockpile <br />previously located from the East Cresson stockpile using CAT 40 -ton articulating haul trucks <br />loaded by a CAT 988 front -end loader. Moisture conditioning of SLF material was performed in <br />place using a tandem -axle water truck and compaction was achieved using a 10 -ton vibratory <br />smooth drum compactor. Nuclear density testing, moisture verification, and depth check testing <br />was performed with results within project specifications. Test locations were surveyed by Ames. <br />Subgrade temperatures were monitored by an AMEC field representative prior to SLF placement. <br />Fill material was not placed until the entire fill area was at or above 32 °F. SLF placed during <br />ambient temperatures below 32 °F averaged 42 °F to 51 °F. <br />Location <br />This Week <br />Cumulative <br />Comments <br />(tons) <br />(tons) <br />E.Cresson Clay Process <br />0 <br />81,150 <br />SLF processing is temporarily paused <br />Total <br />0 <br />81,510 <br />SLF processing is temporarily paused <br />E) Drain Cover Fill (DCF) <br />Drain cover fill (DCF) placement performed in the area shown on Figure 6. The DCF was hauled <br />from the processing area to the placement area using 40 -ton articulating haul trucks loaded by a <br />CAT 988 front -end loader. The DCF was placed in a 2 -foot lift using various CAT dozers except <br />where haul routes were established. Haul routes consisted of four -foot lifts to be spread into 2- <br />foot lifts later. Laborers were present at all times during placement removing debris /sandbags and <br />assisting the dozer operator with lift thickness. All DCF was placed on previously approved <br />primary geomembrane. Fill material placed during ambient temperatures below 32 °F averaged <br />42 °F. AMEC field representatives monitored the DCF placement constantly. <br />Location <br />This Week <br />Cumulative <br />Comments <br />DCF Process <br />0 <br />228,613 <br />DCF processing is temporarily paused <br />Total <br />0 <br />228,613 <br />DCF processing is temporarily paused <br />F) Miscellaneous <br />No work performed during the week. <br />II) Geosynthetics <br />A) Geomembrane Delivery <br />Geomembrane delivery is complete for the Mill Site Earthworks project. <br />MEW Weekly Report WE 10. 13.2012 <br />