RECEIVED <br />. 2Cn'' 1 GT <br />Division a. i:ec!arnation, <br />ameo <br />pr r. <br />MILL SITE EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: Mill Site Earthworks <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Mill Site Earthworks <br />Date: September 22, 2012 <br />Reporting Period: 9/16/2012 through 9/22/2012 <br />Days <br />S <br />I M <br />T <br />W <br />T <br />F <br />S <br />Work Shifts <br />D <br />D <br />D <br />D <br />D <br />D = Day Shift <br />N = <br />Night Shift <br />Project No.: 74201125K0 <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day /Night p Miry, <br />r 1 +' NX� <br />CQA A"- <br />M -vo -a49 <br />Ambient Temperature Range ( °F): Low: 34 °F to 43 °F ( + / -) High: 53 °F to 69 °F <br />AMEC CQA: Personnel On -site through the Reporting Period (See Attachment A). <br />Ames: Work activities resumed on Tuesday, September 18, 2012. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />I) Earthworks <br />A) Subgrade Preparation <br />Subgrade preparation was performed preparing for soil liner fill placement. Moisture conditioning <br />of the subgrade was performed (when necessary) using a tandem -axle water truck. Compaction <br />was performed using a 10 -ton vibratory smooth drum compactor passing over the entire subgrade <br />surface at least four times. The subgrade shown on Figure 2 was inspected and approved by an <br />AMEC field representative for SLF placement. <br />B) Overburden Fill Placement <br />No work performed during the week. <br />C) Slope Contouring <br />No work performed during the week. <br />D) Soil Liner Fill (SLF) <br />Soil liner fill (SLF) placement was performed in the areas shown on Figure 3. Subgrade was <br />approved and moisture conditioned prior to placement using a tandem -axle water truck. <br />Placement was performed using various CAT dozers and a John Deere 120 excavator in a one - <br />foot compacted lift. SLF material was hauled to the Mill Platform from the temporary SLF stockpile <br />previously located from the East Cresson stockpile using CAT 40 -ton articulating haul trucks <br />loaded by a CAT 988 front -end loader. Moisture conditioning of SLF material was performed in <br />place using a tandem -axle water truck and compaction was achieved using a 10 -ton vibratory <br />smooth drum compactor. Control testing was performed during placement to ensure the moisture <br />content and depths were correct during placement. Record testing will be performed prior to <br />geomembrane deployment. <br />MEW Weekly Report WE 09.22.2012 <br />